Updated by Juan Antonio Saiz Usano over 8 years ago
It is currently hard to create plans in the timeline view as when work packages span a weekend the weekend days are counted as working (as are holidays).
- It would be great if you could define a calendar with holidays and non working days so that when a work package taking 3 days that starts on a Friday (assuming Sat & Sun are defined as non working) it will automatically show the end on Tues (not Sun as it currently does).
- This would have the benefit of auto scheduling all work packages that have a ‘following’ relationship set.
- It would be great if you could define a calendar with holidays and non working days so that when a work package taking 3 days that starts on a Friday (assuming Sat & Sun are defined as non working) it will automatically show the end on Tues (not Sun as it currently does).
- This would have the benefit of auto scheduling all work packages that have a ‘following’ relationship set.