Updated by Robin Wagner over 8 years ago
**Preconditions**
- Work package module activated.
**Steps to reproduce**
1. Create work packages A, B, C, D.
2. Using the relations tab in the split screen set precedes relationships starting from A up to D.
3. Activate Gantt chart.
4. Set start / due date for B.
**Actual behavior**
- Relation line between C and D not shown initially (and also relationship created from C to D (precedes) not shown in relations tab of D).
- After zooming it is shown.
**Expected behavior**
- Relation line shown directly.
**Gif**

**QA system**
- qa.openproject-edge.com
- OpenProject 7.4
- Chrome
- Work package module activated.
**Steps to reproduce**
1. Create work packages A, B, C, D.
2. Using the relations tab in the split screen set precedes relationships starting from A up to D.
3. Activate Gantt chart.
4. Set start / due date for B.
**Actual behavior**
- Relation line between C and D not shown initially (and also relationship created from C to D (precedes) not shown in relations tab of D).
- After zooming it is shown.
**Expected behavior**
- Relation line shown directly.
**Gif**

**QA system**
- qa.openproject-edge.com
- OpenProject 7.4
- Chrome