Updated by Robin Wagner over 8 years ago
**Preconditions**
- Work package module activated.
- Work packages A, B, C, D exist.
- Work package A precedes B precedes C precedes D.
- Work package B, C and D have dates set (work package A has no date set).
- Work package A has a child.
**Steps to reproduce**
1. Open work package A in split screen.
2. Go to relation tab.
3. Add an existing child and select work package C.
**Actual behavior**
- Work package C can be selected as child.
- After a short while, an internal error is shown.
**Expected behavior**
- Work package C cannot be selected as a child since it would violate the follows-precedes relationship.
**Screenshot**


**QA system**
- demoproject.openproject.com
- OpenProject 7.3.1
- Chrome
- Work package module activated.
- Work packages A, B, C, D exist.
- Work package A precedes B precedes C precedes D.
- Work package B, C and D have dates set (work package A has no date set).
- Work package A has a child.
**Steps to reproduce**
1. Open work package A in split screen.
2. Go to relation tab.
3. Add an existing child and select work package C.
**Actual behavior**
- Work package C can be selected as child.
- After a short while, an internal error is shown.
**Expected behavior**
- Work package C cannot be selected as a child since it would violate the follows-precedes relationship.
**Screenshot**


**QA system**
- demoproject.openproject.com
- OpenProject 7.3.1
- Chrome