Updated by Robin Wagner over 8 years ago
**Preconditions**
- Work package module activated.
**Steps to reproduce**
1. Go to work package page and activate Gantt chart.
2. Create milestones and set up relations between them.
3. Have one milestone in the middle that has no relation to other work packages. (for example see [this project](https://qa.openproject-edge.com/projects/neues-projekt-bug/work_packages?query_props=%7B%22c%22:%5B%22id%22,%22subject%22,%22type%22,%22status%22,%22priority%22,%22assignee%22%5D,%22tv%22:true,%22tzl%22:%22days%22,%22hi%22:true,%22t%22:%22parent:asc%22,%22f%22:%5B%7B%22n%22:%22status%22,%22o%22:%22o%22,%22v%22:%5B%5D%7D%5D,%22pa%22:1,%22pp%22:100%7D))
**Actual behavior**
- Relations line goes through milestone that has no relations.
- Looks as if the milestones has preceding / following work packages (which is not the case).
**Expected behavior**
- Relations line does not go through milestone without relations.
**Screenshot**

**QA system**
- qa.openproject-edge.com
- OpenProject 7.3
- Chrome
- Work package module activated.
**Steps to reproduce**
1. Go to work package page and activate Gantt chart.
2. Create milestones and set up relations between them.
3. Have one milestone in the middle that has no relation to other work packages. (for example see [this project](https://qa.openproject-edge.com/projects/neues-projekt-bug/work_packages?query_props=%7B%22c%22:%5B%22id%22,%22subject%22,%22type%22,%22status%22,%22priority%22,%22assignee%22%5D,%22tv%22:true,%22tzl%22:%22days%22,%22hi%22:true,%22t%22:%22parent:asc%22,%22f%22:%5B%7B%22n%22:%22status%22,%22o%22:%22o%22,%22v%22:%5B%5D%7D%5D,%22pa%22:1,%22pp%22:100%7D))
**Actual behavior**
- Relations line goes through milestone that has no relations.
- Looks as if the milestones has preceding / following work packages (which is not the case).
**Expected behavior**
- Relations line does not go through milestone without relations.
**Screenshot**

**QA system**
- qa.openproject-edge.com
- OpenProject 7.3
- Chrome