Updated by Robin Wagner about 9 years ago
**Preconditions**
- Work package module activated.
- Work packages with start / due date exist which have similar start / due dates.
**Steps to reproduce**
1. Go to work package list and activate timeline.
2. Right-click on one phase in the timeline and select “Add follower” (or “Add predecessor”).
3. Select another work package with has a similar start /due date.
**Actual behavior**
- The elements in the timeline are not moved according to the new relationship.
- Once one of these work packages is moved in the timeline both work packages are updated correctly.
**Expected behavior**
- Once the relationship is created, the work packages should be displayed correctly in the timeline (e.g. move the following work package).
**Gif**

**QA system**
- qa.openproject-edge.com
- OpenProject 7.0
- Chrome
- Work package module activated.
- Work packages with start / due date exist which have similar start / due dates.
**Steps to reproduce**
1. Go to work package list and activate timeline.
2. Right-click on one phase in the timeline and select “Add follower” (or “Add predecessor”).
3. Select another work package with has a similar start /due date.
**Actual behavior**
- The elements in the timeline are not moved according to the new relationship.
- Once one of these work packages is moved in the timeline both work packages are updated correctly.
**Expected behavior**
- Once the relationship is created, the work packages should be displayed correctly in the timeline (e.g. move the following work package).
**Gif**

**QA system**
- qa.openproject-edge.com
- OpenProject 7.0
- Chrome