Updated by Robin Wagner over 9 years ago
**Preconditions**
- Work package module activated.
- Work package has following relationships.
- Work package has predecessor.
- Work package has date set which is after the end date of the predecessor.
**Steps to reproduce**
1. Try to update date (move to past but after predecessor).
**Actual behavior**
- Error message “Conflicting modifications”.
**Expected behavior**
- Date can be updated (unless there is good reason against it).
**Screenshot**

**QA system**
- OpenProject 6.0.4
- Work package module activated.
- Work package has following relationships.
- Work package has predecessor.
- Work package has date set which is after the end date of the predecessor.
**Steps to reproduce**
1. Try to update date (move to past but after predecessor).
**Actual behavior**
- Error message “Conflicting modifications”.
**Expected behavior**
- Date can be updated (unless there is good reason against it).
**Screenshot**

**QA system**
- OpenProject 6.0.4