Updated by Robin Wagner almost 10 years ago
**Preconditions**
- Work package module activated.
- Work packages exist and have start and end dates.
- Work packages follow each other (e.g. A \> B \> C \> D \> E).
**Steps to reproduce**
1. Open a work package in split screen (e.g. B) and update the end date.
2. Without reload go to later work package (e.g. E) and look at start / end date.
**Actual behavior**
- Date of following work package is not updated.
- Reload is required to show updated date.
**Expected behavior**
- Date is updated right away.
**Screenshot**

**QA system**
- qa.openproject-stage.com
- OpenProject 6.0.3
- Work package module activated.
- Work packages exist and have start and end dates.
- Work packages follow each other (e.g. A \> B \> C \> D \> E).
**Steps to reproduce**
1. Open a work package in split screen (e.g. B) and update the end date.
2. Without reload go to later work package (e.g. E) and look at start / end date.
**Actual behavior**
- Date of following work package is not updated.
- Reload is required to show updated date.
**Expected behavior**
- Date is updated right away.
**Screenshot**

**QA system**
- qa.openproject-stage.com
- OpenProject 6.0.3