**As** a project portfolio manager
**I want to** export a PMflex artefact including project phases and budgets
**so that** they are included as part of the report
**Acceptance criteria**
* Optionally include project budgets
* Budgets are rendered as a planned-cost breakdown per budget
table with the following columns for quantity, description, cost per unit and sum
`Subject`, `Planned`, `Spent`, `Available`, `Spent (ratio)` (Text only)
* Each For each budget shows its id, subject and planned total, then its planned unit costs and planned labor costs as separate groups, each group with a subtotal one row
* The section closes with a total across all budgets of the project
* Amounts the viewer is not allowed to see are left blank, as they are in the budget views
<figure class="image image_resized op-uc-figure" style="width:292px;"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/923932/content"></div><figcaption class="op-uc-figure--description">Mockup</figcaption></figure> Sum row
* Optionally include project lifecycle
* The options are added to the export settings and export dialog
**Technical notes**
* <br>
**Permissions and visibility considerations**
* _To whom is this feature visible?_
* _When is it not visible?_
**Out of scope**
* Graphics like Spent progress bar or Project phase timeline
**I want to** export a PMflex artefact including project phases and budgets
**so that** they are included as part of the report
**Acceptance criteria**
* Optionally include project budgets
* Budgets are rendered as a planned-cost breakdown per budget
`Subject`, `Planned`, `Spent`, `Available`, `Spent (ratio)` (Text only)
* Each
* The section closes with a total across all budgets of the project
* Amounts the viewer is not allowed to see are left blank, as they are in the budget views
<figure class="image image_resized op-uc-figure" style="width:292px;"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/923932/content"></div><figcaption class="op-uc-figure--description">Mockup</figcaption></figure>
* Optionally include project lifecycle
* The options are added to the export settings and export dialog
**Technical notes**
* <br>
**Permissions and visibility considerations**
* _To whom is this feature visible?_
* _When is it not visible?_
**Out of scope**
* Graphics like Spent progress bar or Project phase timeline