Updated by Oliver Günther 10 months ago
### Risk register
* Users can create and describe a risk with built-in and custom fields, including.
* Each risk includes two built-in numeric fields: Separate project module
* `Likelihood` (1–5 scale) Activates the work package type "Risk" when activated in a project
* `Impact` (1–5 scale)
### Scoring
* We calculate
* **Initial Risk Score** = Likelihood × Impact Activates the required custom fields when activated in a project
* We derive a **Residual Risk Score**, either: New "protected" work package type "Risk"
* Manually entered, or Can not be deleted
* Calculated from linked controls/treatments
### Risk Treatment and Actions
* Users can add multiple **Actions** and **Treatment Items** to each risk.
* These items could define deltas on likelihood and impact, causing an observable reduction of the risk over time
* These items could Can not be work packages or other items
renamed (and is automatically translated)
* Residual risk values can be shown and visualized
### Workflow and Status
* Risk items follow a preconfigured status workflow
* Changes to the attributes are journalized
"protected" custom fields
* Risks can Can not be commented on
* A risk has an owner, and should receive notifications
### Reporting
* All changes to:
* Status deleted
* Risk scores
* Linked items
* are logged for traceability.
* PDF Reports can Can not be generated by:
renamed (are automatically translated)
* Status
Impact
* Owner
Probability
* Risk score
### Project Integration
value (Calculated
* Risks are linked to a project or sub-project.
* Optional linking to:
* Work packages
* Meetings
* Documents
### 9\. User Permissions
* Permissions configurable by role:
* View risks
* Manage Risks
* TBD: Additional more fine-grained permissions
<br> Risk management widget for Overview/Dashboard
* Users can create and describe a risk with built-in and custom fields, including.
* Each risk includes two built-in numeric fields:
* `Likelihood` (1–5 scale)
* `Impact` (1–5 scale)
### Scoring
* We calculate
* **Initial Risk Score** = Likelihood × Impact
* We derive a **Residual Risk Score**, either:
* Manually entered, or
* Calculated from linked controls/treatments
### Risk Treatment and Actions
* Users can add multiple **Actions** and **Treatment Items** to each risk.
* These items could define deltas on likelihood and impact, causing an observable reduction of the risk over time
* These items could
### Workflow and Status
* Risk items follow a preconfigured status workflow
* Changes to the attributes are journalized
* A risk has an owner, and should receive notifications
### Reporting
* All changes to:
* Status
* Risk scores
* Linked items
* are logged for traceability.
* PDF Reports can
### Project Integration
* Optional linking to:
* Work packages
* Meetings
* Documents
### 9\. User Permissions
* Permissions configurable by role:
* View risks
* Manage Risks
* TBD: Additional more fine-grained permissions
<br>