Content
Updated by Niels Lindenthal 4 days ago
* In a project template phases can have a relative duration, e.g.:
* Initiation: 10%
* Planning: 20%
* Excecuting: 60 %
* Closing: 10%
* When a new In the project is initiated based on the template the relative durations of the phases creation form there are copied to the new project.
three fields:
* If the user then adds Project start date
* Project end date
* Duration
* When setting a project start date and a project finish date in the project overview the other dates for from the project phases are automatically calculated based on this input. derived
* Initiation: 10%
* Planning: 20%
* Excecuting: 60 %
* Closing: 10%
* When a new
* Project end date
* Duration
* When setting