# Feature SPPM-86 - Fixed set of project phases and gates editable on project overview page

Project: Stream Project Portfolio Management
Status: closed
URL: https://community.openproject.org/work_packages/SPPM-86

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | 16.1.0 |
| Votes |  |
| List |  |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Use cases

_No work packages_

## Features and Chunks

| ID | Subject | Type | Status | Assignee | Target versions | Spent time |
| --- | --- | --- | --- | --- | --- | --- |
| SPPM-105 | Set up and seed Stages and Gates structures | Implementation | closed |  | 15.1.0 |  |
| SPPM-106 | Add Stages and Gates to the Project Overview page | Implementation | closed |  | 15.2.0 |  |
| SPPM-108 | Put life cycle steps colors into styles.css | Implementation | closed |  | 15.1.0 |  |
| SPPM-115 | Apply view permissions on the Project List page | Implementation | closed |  | 15.2.0 |  |
| SPPM-118 | Allow Gate to be overlapping a Stage | Implementation | closed |  | 15.2.0 |  |
| SPPM-124 | Add documentation for form previews Stages and Gates Overview dialog | Implementation | closed |  | 15.3.0 |  |

## Bugs and other work packages

_No work packages_

## Technical Details

| Attribute | Value |
| --- | --- |
| Module |  |
| Feature Flag |  |
| Requires doc change | Yes |
| Enterprise plan |  |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups |  |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Feature Lead |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

**As** a project admin  
**I want to** organize the project into dedicated stages and gates  
**so that** it is easier to communicate about the step the project is in and what that means for the progress.

*Note: This is but the first in a number of features which will greatly increase the versatility of phases*

**Acceptance criteria**

  - Create a feature flag for the feature hiding all traces of it.

  - Seed a fixed set of phases and gate types (for both existing and new instances of OpenProject)
    
      - Those phases and gate types are similar to work package types. They define which phases/gates exist in a project. Each project will then receive instances of those types (see below).
    
      - Seeded phases:
        
          - Initiating: \#F7983A,
        
          - Ready for Planning:  \#682D91,
        
          - Planning: \#F05823,
        
          - Ready for Executing: \#682D91,
        
          - Executing: \#EC038A,
        
          - Ready for Closing: \#682D91,
        
          - Closing: \#B1D13A
    
      - The colors are newly created if they do not exist (in Administration -\> Colors).
    
      - The seeded phases and gates are internationalized (during seeding process, can not be changed later).

  - Existing projects will not have the stages and gates enabled.

  - New projects will not have the stages and gates enabled by default.

  - The project overview page has an area called "Project lifecycle" in the sidepanel above the project attributes section which displays the dates configured for each stage/gate in the current project.
    
      - Viewing the phases/gates requires a project permission.
        
          - Name: View project phases and gates
        
          - Pre-seeding: All project roles get this permission
        
          - Migrations on existing installations: All project roles get this permission (since they are empty no data is leaked). This includes anonymous and non-members.
    
      - In case all stages and gates are disabled in the project (<mention class="mention" data-id="58163" data-type="work_package" data-text="##58163">##58163</mention>), the section is hidden.

  - The area showing the phases/gates in the current project's overview page allows the user to modify the dates of each stage/gate.
    
      - Modifying the dates of the phases/gates requires a project permission different from the view permission.
        
          - Name: Edit project phases and gates (~~includes~~ requires view permission)
        
          - Pre-seeding: The role project admin gets this permissions.
        
          - Migrations on existing installations: All project roles that get this permission that have the permission "edit project".
    
      - Phases and gates have an input field to modify their date (range).
        
          - The user is supported when modifying the dates by the OpenProject date picker
            
              - For gates, it is a single date date picker.
            
              - For stages, it is the range date picker.
        
          - A stage will either have no date set at all or both dates set. It cannot have only the start or the end date set.
        
          - The start date of a stage has to be before the end date.
        
          - The minimum length for a stage is one day: This means a stage can start and end on the same date.
        
          - There is no maximum length for a stage.
        
          - Having gaps between stages/gates is allowed.
        
          - Stages cannot have overlapping dates. Gates can overlap the start/end date of a stage. But only exactly the start/end date. The date of a gate cannot be between a stage's dates.
            
              - A gate's date can not be the same as another gate's date.
        
          - The dates entered have to reflect the order configured for phases/gates in the administration.
            
              - e.g. It is not possible to define the dates of the 'Initiating' phase to be after the dates of the 'Closing' phase.
        
          - Phases/gates of the child project limited are not limited by the dates in the parent project.
            
            <br>

**Out of scope**

  - Automatic scheduling for inserting the dates of stages and gates in the overview page.
    
      - including maintaing a fixed lag

  - Scheduling by insertion of a duration.

  - Inheritance to sub projects

  - Seeding of phases/gates for demo projects (<mention class="mention" data-id="58303" data-type="work_package" data-text="##58303">##58303</mention>)

**Reference**

  - The stages are [taken from PM2](https://www.pm2alliance.eu/wp-content/uploads/2024/02/pm%C2%B2-project-management-methodology-NO0523520ENN.pdf)

**Figma**

<https://www.figma.com/design/4Z950sfYbceOqUN6sFV7Mr/Project-management%3A-Stages-and-Gates?node-id=1-10673&amp;node-type=frame&amp;t=cGwFE1QlfVr4tS33-0>