# Epic SPPM-7 - Project start and finish dates and durations for project and project phases

Project: Stream Project Portfolio Management
Status: in specification
URL: https://community.openproject.org/work_packages/SPPM-7

## Detailed specification

### Motivation and background information

### Acceptance criteria

  - Project start and finish dates
    
      - For every project a start date can be defined. This start date is optional.
    
      - The start date of the first phase is defined by the the project start date.

  - Project durations
    
      - Can be entered independently of a project start and finish date, e.g. in case of a project template.
    
      - Project durations are automatically updated based on changes of project start and finish date.

  - Phase durations
    
      - The duration is defined as all working days between the start and finish date of a duration.
    
      - The duration can be changed in the date picker of a phase.
    
      - The duration of phases can be defined without a phase start and finish date. This means that a phase might have a duration without having dates set.

  - Project settings -\> Lifecycle
    
      - There is an input field for the project start date (optional).
    
      - There is an input field for the project duration (optional). This field is deactivated as soon as there phases defined.
    
      - The project finish date is read only.
    
      - The project start date cannot be deactivated for a project.
    
      - Changing the project start date changes the start date of the first phase in the project.

  - Project list
    
      - The project list receives columns for displaying the project start and the finish date.
    
      - The project list can be filtered by the projects' dates.

  - Permissions and visibility considerations
    
      - No additional permissions for durations and project start and finish dates
        
          - View project phases
        
          - Edit project phases

  - Project overview
    
      - The project dates are always displayed in project overview. They can not be deactivated in the project settings.

### Out of scope

*   Baseline comparison
    
*   Changes to the project creation forms.
    
*   Additional permissions
    
*   Lag between phases and gates

| Attribute | Value |
| --- | --- |
| Mockups | https://www.figma.com/design/4Z950sfYbceOqUN6sFV7Mr/Project-lifecycle--Phases-and-Phase-gates?node-id=2789-84523&t=MFYNpdGDyKGM0ccU-1 |

## Planning

| Attribute | Value |
| --- | --- |
| Roadmap |  |
| Date |  |
| Votes |  |
| List | cProject |
| Target versions |  |
| Relevance |  |

## Subitems

_No work packages_

## Bugs and other work packages

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Module | Modules and project features / Project lifecyle - phases and gates |
| Enterprise plan | Community (COM) |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Feature Lead |  |
| Designer |  |
| Developers | OP Dev Polaris Team |
| Requested by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| Work | 120d 0h |

## Description

**As a** project manager  
**I want to** be able to set a project start and finish date and a duration  
**So that I** can communicate the high-level planning to my stakeholders, e.g. the project portfolio manager.

<br>

<img class="image_resized op-uc-image op-uc-image_inline" style="width:519px;" src="/api/v3/attachments/621120/content">

<br>

<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/621124/content">

<br>

<br>