## Details

| Attribute | Value |
| --- | --- |
| Date | 2026-02-04 – 2026-02-25 |
| Priority | Medium |
| Module | Modules and project features / Project attributes, Modules and project features / Project lifecyle - phases and gates |
| Target versions | 17.2.0 |
| Observed in versions | 17.2.0 |
| Bug found in version (deprecated) | 17.2.x |
| Requires doc change | No |
| Accessibility | No |
| Pull preview |  |
| List |  |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers | Ivan Kuchin |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Planning

| Attribute | Value |
| --- | --- |
| Relevance |  |

## Costs

| Attribute | Value |
| --- | --- |
| Votes |  |
| Work |  |
| Labor costs |  |

## Description

### Steps to reproduce

1.  Have a comment enabled on a project attribute.
    
2.  Have project template with PIR enabled.
    
3.  Activiate the project attribute for the PIR.
    
4.  Fill in a value for the comment.
    
5.  Finish the PIR
    
6.  Take a look into the PDF of the PIR
    

### What is the buggy behavior?

*   The comment field is not included in the PIR
    

### What is the expected behavior?

1.  The comment field is printed out after the project attribute it is enabled on.