# Epic SPPM-18 - Project life cyle with phases and gates - Step 1: customization and configuration 

Project: Stream Project Portfolio Management
Status: closed
URL: https://community.openproject.org/work_packages/SPPM-18

## Detailed specification

### Motivation and background information

### Acceptance criteria

*   Administration
    
    *   There is a feature flag to activate the new feature.
        
    *   EE: In the administration, there is a UI to define stages and gates (Administration -&gt; Project -&gt; Stages and gates)
        
    *   There is setting to differentiate a gate from a stage:
        
        *   A gate has only one date.
            
        *   A gate is visualized as a &quot;diamond&quot;.
            
    *   There is a UI to select a color for each stage type/gate type.
        
*   Project settings
    
    *   Stages and gates can be activated and deactivated at a project level (similiar to project attributes). A dedicated project permission is required to do this.
        
    *   When copying projects the active status of gates and stages are copied too.
        
*   Project overview
    
    *   In the Project Overview there is a UI to show and edit stages and gates that are enabled for that project.
        
    *   There is a project permission to **see all** stages and gates in a project.
        
    *   There is a project permission to **edit all** stages and gates in a project.
        
    *   There is an edit action to be able to edit the dates for each stage and gate.
        
*   Project list
    
    *   Select individual stages and gates as columns for a project list (there is no option to show/hide the columns for all stages and gates).
        
    *   The stage/gate is indicated in the column header as colored icon next to the name.

### Out of scope

*   Dedicated end point for start and finish date of a project
    
*   Project types
    
*   Automatic scheduling and duration
    
*   Inheritance/sharing
    
*   Timeline/Gantt
    
*   Journalization of changes
    
*   Assignments to work packages
    
*   Iterations/sprints

| Attribute | Value |
| --- | --- |
| Mockups | https://www.figma.com/design/4Z950sfYbceOqUN6sFV7Mr/Project-Portfolios--Stages-and-Gates?node-id=2241-25240 |

## Planning

| Attribute | Value |
| --- | --- |
| Roadmap |  |
| Date | 2025-06-19 |
| Votes |  |
| List | cProject |
| Target versions |  |
| Relevance |  |

## Subitems

| ID | Type | Subject | Status | Assignee | Target versions | Project | Priority | Spent time |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| OP-16366 | Feature | Prevent autocomplete on date picker input fields | closed |  | 15.3.0 | OpenProject | Medium |  |
| SPPM-86 | Feature | Fixed set of project phases and gates editable on project overview page | closed |  | 16.1.0 | Stream Project Portfolio Management | Medium |  |
| SPPM-87 | Feature | Project phase columns on project list | closed |  | 16.1.0 | Stream Project Portfolio Management | Medium |  |
| SPPM-88 | Feature | Global phase administration | closed |  | 16.1.0 | Stream Project Portfolio Management | Medium |  |
| SPPM-90 | Feature | Project specific phase administration | closed |  | 16.1.0 | Stream Project Portfolio Management | Medium |  |
| SPPM-119 | Feature | Optimize life cycle modal UX | closed |  | 16.1.0 | Stream Project Portfolio Management | Medium |  |

## Bugs and other work packages

| ID | Type | Subject | Status | Assignee | Target versions | Module |
| --- | --- | --- | --- | --- | --- | --- |
| SPPM-125 | Bug | Unable to use the date picker for stages | closed |  | 15.2.0 |  |
| SPPM-117 | Bug | Moving a stage/gate with filled in dates within the lifecycle might create invalid dates | rejected |  | 15.3.0 |  |
| SPPM-130 | Bug | User can't save lifecycle modal if project is invalid | closed |  | 16.1.0 |  |

## Details

| Attribute | Value |
| --- | --- |
| Module | Modules and project features / Project list |
| Enterprise plan | Enterprise / Premium (PRE) |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee | Niels Lindenthal |
| Accountable |  |
| Product manager |  |
| Feature Lead |  |
| Designer | Marc Alcobé |
| Developers | OP Dev Polaris Team |
| Requested by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| Work | 180d 0h · Σ 180d 0h |

## Description

**As a** project portfolio manager

**I want to** have an overview of the project timeline of the projects in different portfolios

**So that I** can more easily understand the status of each project in order to make portfolios decisions.

<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/495808/content">

<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/495809/content">

<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/495810/content">