# Epic SPAR-67 - Scheduling mode "As soon as possible" to automatically reschedule successors

Project: Stream Planning and Reporting
Status: closed
URL: https://community.openproject.org/work_packages/SPAR-67

## Detailed specification

### Motivation and background information

### Acceptance criteria

*   Edit lag to follow-precedes-relations
    
*   There is a new scheduling mode &quot;Automatic scheduling (start as soon as possible)&quot;.
    
*   When this mode is activated users can not manually change the date of this work package in the date picker, team planner or Gantt view.
    
*   In case the user wants to change the date the user needs to switch to the manual scheduling mode first.

### Out of scope

| Attribute | Value |
| --- | --- |
| Mockups | https://www.figma.com/design/HrWVktq0SsGI2dqqIKQ11M/Scheduling---Lag-and-Modes?node-id=175-3641 |

## Planning

| Attribute | Value |
| --- | --- |
| Roadmap |  |
| Date |  |
| Votes | 6 |
| List | cProject |
| Target versions |  |
| Relevance |  |

## Subitems

| ID | Type | Subject | Status | Assignee | Target versions | Project | Priority | Spent time |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| SPAR-1 | Feature | Edit lag to follow-precedes-relations | closed |  | 15.2.0 | Stream Planning and Reporting | Medium |  |
| SPAR-115 | Feature | When adding new relations, auto-scroll to show the newly added relation | closed |  | 15.2.0 | Stream Planning and Reporting | Medium |  |
| SPAR-125 | Feature | Improve comprehensibility of the "Add relations" modal | closed |  | 15.2.0 | Stream Planning and Reporting | Medium |  |
| SPAR-104 | Feature | Indicate that there are work package relations which the user has no permission to see | closed |  | 15.3.0 | Stream Planning and Reporting | Medium |  |
| SPAR-121 | Feature | Add trailing unit for input fields in datepicker and lag field | closed |  | 15.3.0 | Stream Planning and Reporting | Medium |  |
| SPAR-145 | Feature | Relations tab: Show a single date when start and finish dates are the same | closed |  | 15.3.0 | Stream Planning and Reporting | Medium |  |
| SPAR-23 | Feature | New scheduling mode: automatic (start as soon as possible) | closed |  | 15.4.0 | Stream Planning and Reporting | Medium |  |
| SPAR-133 | Feature | Automatic scheduling mode: make it possible to enter Finish date by direct input or by clicking on the mini calendar | closed |  | 15.5.0 | Stream Planning and Reporting | Medium |  |
| SPAR-146 | Feature | Improve date picker rendering in mobile screens | closed |  | 15.5.0 | Stream Planning and Reporting | Medium |  |
| SPAR-106 | Open Point | Should we have a new icon for "automatically scheduled", like the pin for manual? | decided | Parimal Satyal |  | Stream Planning and Reporting | Medium |  |

## Bugs and other work packages

| ID | Type | Subject | Status | Assignee | Target versions | Module |
| --- | --- | --- | --- | --- | --- | --- |
| SPAR-223 | Bug | Some dates and scheduling mode are lost when creating project from template | closed |  | 16.0.1 |  |
| SPAR-106 | Open Point | Should we have a new icon for "automatically scheduled", like the pin for manual? | decided | Parimal Satyal |  |  |

## Details

| Attribute | Value |
| --- | --- |
| Module |  |
| Enterprise plan | Community (COM) |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Designer |  |
| Developers | Christophe Bliard |
| Requested by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| Work | 90d 0h · Σ 92d 0h |

## Description

**As** a project manager/team manager  
**I would like** to automatically reschedule all successors when planing to finish a predecessor earlier  
**so that** changing the finish date of a predecessor is a reversible action. I don't have to move all successors manually.

<img class="image_resized op-uc-image op-uc-image_inline" style="width:274px;" src="/api/v3/attachments/240496/content">

<img class="image_resized op-uc-image op-uc-image_inline" style="width:267px;" src="/api/v3/attachments/240497/content">