# Feature SPAR-285 - Visual baseline comparison in the Gantt chart

Project: Stream Planning and Reporting
Status: rejected
URL: https://community.openproject.org/work_packages/SPAR-285

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | Wish List |
| Votes | 2 |
| List |  |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Features and Chunks

_No work packages_

## Bugs and other work packages

_No work packages_

## Technical Details

| Attribute | Value |
| --- | --- |
| Module | Modules and project features / Baseline |
| Feature Flag |  |
| Requires doc change | No |
| Enterprise plan |  |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups |  |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

**As a project manager** using baselines to track progress and deviations, I want to see one or more selected baselines rendered as additional bars directly in the Gantt chart, so that I can identify schedule deviations (ahead of / behind plan) at a glance without opening the work package list details.

**Acceptance criteria**

*   In the Gantt view, the user can activate a baseline overlay via the existing baseline selection.
    
*   For each work package, the baseline is displayed as a second bar next to (e.g. below) the current work package bar.
    
*   The overlay also applies to milestones (and phases), so that milestone shifts against the baseline are visible directly in the chart.
    
*   The user can freely choose which baseline to display (e.g. &quot;yesterday&quot;, &quot;last working day&quot;, a specific date, or a saved baseline).
    
*   It is possible to display and compare multiple baselines simultaneously (e.g. Baseline 1 and Baseline 2 next to the current bar). When multiple baselines are shown, there is a clear arrangement (stacking order, row height) and visual distinction between them (e.g. different grey shades plus a legend), so that a trend across several baseline dates remains recognizable at a glance.
    
*   The baseline bar(s) are styled in grey and/or semi-transparent to be clearly distinguishable from the current (colored) plan bar.
    
*   Each baseline bar is positioned exactly at its original start and finish date; the current bar remains unchanged.
    
*   Deviations are immediately recognizable: if the current bar starts/ends earlier or later than the baseline bar, this is visible without any additional interaction.
    
*   The direction of the deviation (ahead of / behind plan) is visually indicated (e.g. via color coding or a delta connector between the baseline finish and the current finish), and the deviation in days is shown in the bar&#x27;s tooltip.
    
*   The overlay works consistently with existing Gantt features (zoom levels, collapsing/expanding, filtering).
    
*   Work packages without baseline values (e.g. created after the baseline date) show no baseline bar.
    

**Technical notes**

*   Reference for expected UX: Jira Advanced Roadmaps baseline display (screenshot see activity tab).
    

**Permissions and visibility considerations**

*   To whom is this feature visible?
    
    *   To all users who have permission to view the Gantt chart / work packages of the project; the baseline overlay follows the same visibility rules as the existing baseline function in the work package table.
        
*   When is it not visible?
    
    *   When no baseline is selected/activated, when the user lacks permission to view the work packages, or for work packages that have no data for the selected baseline date.
        

**Translation considerations**

*   Key terms and phrases in the key languages
    
    *   &quot;Show baseline in Gantt chart&quot; (EN) / &quot;Baseline im Gantt-Diagramm anzeigen&quot; (DE)
        
    *   Tooltip labels such as &quot;Original start date&quot; / &quot;Ursprüngliches Startdatum&quot; and &quot;Original finish date&quot; / &quot;Ursprüngliches Enddatum&quot;
        
    *   Deviation labels such as &quot;Deviation&quot; / &quot;Abweichung&quot;, &quot;ahead of plan&quot; / &quot;vor Plan&quot; and &quot;behind plan&quot; / &quot;hinter Plan&quot;
        

**Out of scope**

*   Changes to the existing baseline display in the work package list/table.
    
*   Automatic scheduling or re-planning based on baseline deviations.
    
*   Baseline variance reports/exports (numeric deviation reports beyond the visual overlay); the in-bar tooltip deviation in days is part of the visual overlay and not considered a separate report.
    
*   Editing or moving the baseline bars (baselines remain read-only).