# Bug SPAR-277 - Update from OpenProject 13 to newer versions causes DB inconsistencies with progress values

Project: Stream Planning and Reporting
Status: closed
URL: https://community.openproject.org/work_packages/SPAR-277

## Open points

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | High |
| Module | Modules and project features / Work packages, Modules and project features / Progress and work estimates |
| Target versions | 16.3.2 |
| Observed in versions | 16.2.0 |
| Bug found in version (deprecated) | 16.2.x |
| Requires doc change | No |
| Accessibility | No |
| Pull preview |  |
| List |  |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers | Christophe Bliard |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Planning

| Attribute | Value |
| --- | --- |
| Relevance |  |

## Costs

| Attribute | Value |
| --- | --- |
| Votes |  |
| Work |  |
| Labor costs |  |

## Description

Originally bug report <mention class="mention" data-id="66552" data-type="work_package" data-text="##66552">##66552</mention> from which there was 2 issues. This one is about the inaccurate progress values after migration.

### Steps to reproduce

1.  Install OpenProject 13

2.  Create multiple tasks and set estimated time

3.  Set some arbitrary remaining time and a mismatching/unproportional completion percentage

4.  Upgrade to version 14 or higher

Context: We've migrated from the latest 13.x branch version to latest 14.x, then upgraded PostgreSQL to v17 and moved OpenProject straight to 16.2.2 right after that

### What is the buggy behavior?

  - The migration to v14+'s new time/percentage behaviour is inaccurate and miscalculates percentages
    
      - Example:
    
      - before migration: estimated time = 0.25h, remaining time = 0h, done ratio = 75%
    
      - during migration to version 14, remaining time gets calculated to 0.0625h, then rounded to 0.06h
    
      - after migration: estimated time = 0.25h, remaining time = 0.06h, done ratio = 75%
        
          - Percentage should be 76% but ends up as 75% during migration

  - Trying to update such tasks fails because of validation errors with a 422. For start/end-date the error is silent, so pressing on save ends up doing nothing. It's because it's a modal.

  - Once you open the estimated/remaining-time and percentage popups, it will show (in red, on % completed), that the number is mismatching the time values
    
      - This seems... pointless? Given v14's changelog stated that this value is system calculated, not user input, so why validate?

\*\*WORKAROUND (\*\*Works, but hacky): Manual DBupdate using this query: 

  - update work\_packages set done\_ratio = ((estimated\_hours-remaining\_hours)/estimated\_hours\*100) where estimated\_hours IS NOT NULL and estimated\_hours \!= 0;

### What is the expected behavior?

1.  OpenProject auto-corrects the percentage on load (serverside)

2.  OpenProject does not display an error if the value is inside an acceptable range

### Analysis

This happens because progress values are rounded all the time when derived from the other: work and remaining work values are rounded to 2 decimal places. % complete is rounded to integer.

When validating values coherence, when work is very low there is a range of acceptable values for % complete. Similarly, when work is very high, there is a range of acceptable values for remaining work.

The validations currently do not account for this precision loss and displays an error if the % complete value is not the one given by the computation.

This is not limited to migration to version 14. It also happens on a live instance:

**Other reproduction steps**:

  - Open the progress modal

  - Set work to 0.25h

  - Set % complete to 75%

  - \=\> remaining work is derived to 0.06h and an error is displayed, depsite being calculated by the app.  
    <img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/770617/content">

**Another reproduction steps**:

This one uses status based to force using 75% and rounded remaining work

  - Use status-based mode

  - Set "in-progress" status to be 75% complete

  - set a work package to have status = in-progress and work = 0.25h
    
      - \=\> remaining work gets updated to 0.06h

  - Now switch back to work-based mode

  - Then try to open the progress modal =\> error about % complete mismatch is displayed

  - Or try to change Priority =\> error 422 due to % complete mismatch

### Screenshots and other files

Example error. Context: manually removing the 75% will make it auto-fill back to 75%, setting remaining time to 0 or setting the percentage to 76% fixes the current task/package.  
Once the bug has been fixed, the browser will auto-complete the % to the correct 76% instead if one attempts to blank the field.

<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/770606/content">

### Environment information

**OpenProject installation type**

  - Selfhosted, Packaged installation
    
      - Ubuntu 20.04.6 LTS

**OpenProject version**

*16.2.2*

**Browser**

- [x] Chrome
- [x] Firefox
- [ ] Safari
- [ ] Mobile Safari
- [ ] Other (please specify)

**Operating System**

- [x] Windows
- [ ] Mac OS X
- [ ] Mobile iOS
- [ ] Mobile Android
- [ ] Linux (please specify distro)
- [ ] Chrome OS
- [ ] Other (please specify)

**Language**

*English and German*