# Feature OP-9902 - Global Gantt Chart for all projects

Project: OpenProject
Status: new
URL: https://community.openproject.org/work_packages/OP-9902

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | Wish List |
| Sprint |  |
| Backlog bucket |  |
| Votes | 7 |
| List |  |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Features and Chunks

_No work packages_

## Bugs and other work packages

_No work packages_

## Technical Details

| Attribute | Value |
| --- | --- |
| Module | Modules and project features / Gantt view, Modules and project features / Project list |
| Feature Flag |  |
| Requires doc change | No |
| Enterprise plan |  |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups |  |
| Found in mobile app version |  |
| Follow-up feedback e-mail |  |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

**As** an open project user and a Project Manager/Engineer/Sales Person/Drafter/Service Man at work,  
**I want to** be able to Gant Chart out all my projects by an overall project start and finish date.  
**so that** I can see where overlaps in projects/future projects will be without having to scroll and look though a ton of work packages to see other projects.

**Acceptance criteria**

*   There should be a page or filter for project Gant Chart. Maybe useful in the &quot;view all projects&quot; page or a dashboard page
*   This will be a view of all projects compressed into one line per projects.
*   Ex. 
    *   projects are: A, B, C, D
    *   Each project has the same or similar work packages: 1,2,3,4,5,6
    *   The Gant Chart would have 4 rows, one for A, one for B, one for C and one for D
    *   In each row there would be colored sections for each of the work packages 
    *   there could be some special denotation for milestones(diamond marks) or if any work packages overlap on time within a project.