# Bug OP-9065 - Unable to move task on taskboard if story added late to the sprint

Project: OpenProject
Status: closed
URL: https://community.openproject.org/work_packages/OP-9065

## Open points

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Module |  |
| Target versions | 12.0.0 |
| Observed in versions |  |
| Sprint | 12.0.0 |
| Backlog bucket |  |
| Bug found in version (deprecated) |  |
| Found in mobile app version |  |
| Follow-up feedback e-mail |  |
| Requires doc change | No |
| Accessibility | No |
| Pull preview |  |
| List |  |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Planning

| Attribute | Value |
| --- | --- |
| Relevance |  |

## Costs

| Attribute | Value |
| --- | --- |
| Votes |  |
| Work |  |
| Labor costs |  |

## Description

### **Environment**:

OP 11.3+

### **Logs**

https://sentry.openproject.com/sentry/saas-openproject-prod/issues/12779

### **Steps to reproduce:**

1.  Have a project with backlogs active and a version configured for backlogs
2.  Outside of backlogs, e.g. in the work package list create a story and three tasks
3.  Assign the story to the version covered by backlogs
4.  Go to the backlogs taskboard
5.  Try to move the last task, without changing the taskboard cell, between the first and the second task

### **Actual Behavior**

An error is displayed on the task and the change is not persisted

### **Expected Behavior**

No error displayed and the change persisted.

### Note

The problem can be circumvented by ordering the tickets from the top down, so first moving the intended ticket to the first position, then the second, ...