# Bug OP-8733 - Changing a project's status together with the project's parent loses change to status

Project: OpenProject
Status: closed
URL: https://community.openproject.org/work_packages/OP-8733

## Open points

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Module |  |
| Target versions | 11.3.0 |
| Observed in versions |  |
| Sprint | 11.3.0 |
| Backlog bucket |  |
| Bug found in version (deprecated) |  |
| Found in mobile app version |  |
| Follow-up feedback e-mail |  |
| Requires doc change | No |
| Accessibility | No |
| Pull preview |  |
| List |  |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Planning

| Attribute | Value |
| --- | --- |
| Relevance |  |

## Costs

| Attribute | Value |
| --- | --- |
| Votes |  |
| Work |  |
| Labor costs |  |

## Description

### **Steps to reproduce:**

1.  Go to a project's settings page
2.  Change the parent of the project
3.  Change the status of the project
4.  Click "Save"
5.  Reload

### **Actual Behavior**

The change to the parent is kept, the change to the status is lost.

### **Expected Behavior**

Both changes are presisted.