# Bug OP-7407 - Work package status % is not added up for parents

Project: OpenProject
Status: closed
URL: https://community.openproject.org/work_packages/OP-7407

## Open points

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | High |
| Module |  |
| Target versions | 13.3.1 |
| Observed in versions | 10.4.0 |
| Sprint | 13.3.1 |
| Backlog bucket |  |
| Bug found in version (deprecated) | 10.4.x |
| Found in mobile app version |  |
| Follow-up feedback e-mail |  |
| Requires doc change | No |
| Accessibility | No |
| Pull preview |  |
| List |  |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Planning

| Attribute | Value |
| --- | --- |
| Relevance |  |

## Costs

| Attribute | Value |
| --- | --- |
| Votes |  |
| Work |  |
| Labor costs |  |

## Description

### **Environment**:

Your OpenProject Version: **OpenProject 10.4.0**

Operating System / Browser / Language: ubuntu 18.04, German, Google Chrome and Firefox

### **Logs**

no errors

### **Steps to reproduce:**

Set up a task structure like this:

![](/api/v3/attachments/18627/content)

Setup open project such that the %-done is calculated from the work package status:

![](/api/v3/attachments/18628/content)

I assigned:

*   new - 0%
*   in progress - 50%
*   done - 100%

  

###   

### **Actual Behavior**

As you can see in the image, the %-done of task &quot;a&quot; (parent) does not reflect the actual status of the sub-tasks. 

### **Expected Behavior**

I would have expected (100+100+50)/300=83% or something like that. But not 0%. This is what I found it to be in the forums and in the offiical documentation.