# Feature OP-3883 - Work package Relation Follows - Start & end dates not updated

Project: OpenProject
Status: new
URL: https://community.openproject.org/work_packages/OP-3883

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | Wish List |
| Sprint |  |
| Backlog bucket |  |
| Votes | 1 |
| List |  |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Features and Chunks

_No work packages_

## Bugs and other work packages

_No work packages_

## Technical Details

| Attribute | Value |
| --- | --- |
| Module |  |
| Feature Flag |  |
| Requires doc change | No |
| Enterprise plan |  |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups |  |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Feature Lead |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

Hello Team -

Observe one basic error in Work package - Relation “Follows” functionality .

Pre-conditions

  - WP1 - Estimated effort - 16 hrs , Start date - 10Jun , End Date - 12Jun
  - WP2 - Estimated effort - 24 hrs Follows WP1 

Expected Behavior

  - WP2 - Start date - 13Jun , End date - 15Jun ( Considering estimated effort of 24 hours)

Observed Behaviour

  - WP2 - Start date - 13Jun , End date - 13Jun
  - This is causing false estimate report in timelines 

Request further advise on same.