# Feature OP-12996 - Key binding to allow users to preserve delay for followers when rescheduling in Gantt view

Project: OpenProject
Status: new
URL: https://community.openproject.org/work_packages/OP-12996

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | Wish List |
| Sprint |  |
| Backlog bucket |  |
| Votes | 1 |
| List |  |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Features and Chunks

_No work packages_

## Bugs and other work packages

_No work packages_

## Technical Details

| Attribute | Value |
| --- | --- |
| Module |  |
| Feature Flag |  |
| Requires doc change | Yes |
| Enterprise plan |  |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups |  |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Feature Lead |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

**As** a project manager or member,  
**I want to** have the option be able to reschedule work packages such that delay is preserved for followers  
**so that** I don't have to individually reschedule all followers

### Context

  - This feature is based on a [request by user Bernard Grey in a comment](https://community.openproject.org/work_packages/44053#activity-19).
  - This feature simply proposes a short-cut solution to preserve delay at a per-modification level, not as an inherent property of a work package relation. For the latter, see related feature <mention class="mention" data-id="22360" data-type="work_package" data-text="#22360">#22360</mention>.

### **Acceptance criteria**

  - Preserve the existing behaviour of ignoring delay between preceding/following work packages by default when moving them in Gannt view but allow a manual override at an action level:
      - If a user reschedules a work package by moving it or sliding a start/finish date in the Control key held, it preserves the relative delay values (the gap of \# number of days before) for all follower work packages.
      - This means that if she reschedules a work package with 4 followers to start *and* end N days earlier whilst holding the Control key, all 4 followers would shift their start and end dates by 4 days earlier.

### Open

  - *\[open\] Should there be another key binding for preserving delay between current work package and precedessor, so that moving a work package in the middle of a chain forwards pulls predecessors backwards in time whilst not affecting followers?*

### Out of scope

  - Any option outside of the Gantt chart, for example in the date picker,  *to also reschedule followers* might mean having to introduce a certain constrain attribute or mode. This will be handled in a different feature: 
    
    <mention class="mention" data-id="22360" data-type="work_package" data-text="###22360">###22360</mention> 

### **Notes**

*From* [*Bernard Gray's original comment*](https://community.openproject.org/work_packages/44053#activity-19)*:*

>  I understand this gets complicated when calculating for the working day feature, however I strongly doubt it's impossible.
> 
> **Use Case:**
> 
> We have a planning department using openproject in a heavily templated fashion for new product development/changes (of which we have many) and the speed that they are able to create from/adjust the templated projects can be significantly increased with this feature.