# Feature OP-12956 - Auto-calculate health of a project using deviation between planned vs. actual progress

Project: OpenProject
Status: new
URL: https://community.openproject.org/work_packages/OP-12956

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | Wish List |
| Sprint |  |
| Backlog bucket |  |
| Votes | 1 |
| List |  |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Features and Chunks

_No work packages_

## Bugs and other work packages

_No work packages_

## Technical Details

| Attribute | Value |
| --- | --- |
| Module |  |
| Feature Flag |  |
| Requires doc change | No |
| Enterprise plan |  |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups |  |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Feature Lead |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

**As** a _Project Manager_   
**I want** _the system to calculate the health of the project, taking the deviation between the percentage of progress planned globally vs. The percentage of real progress globally_  
**so that** _I am able to visualize whether the project is on time, late or critical._

**Acceptance criteria**

*   _The system must show at the top of the schedule the percentage of global planned progress, the percentage of global real progress._
*   _The system must have a configuration module to be able to parameterize the margin in which the task is considered behind._
*   _The system must show at the top of the schedule the status of the project indicating if it is: ongoing, closed, to start._
*   _The system must show at the top of the schedule the health of the project indicating whether: on time, late or critical taking into account the tolerance margins for deviation._

**Current behavior**  
The tool only allows the registration of the real progress percentages per task, but does not calculate the percentage of global real progress of the project or calculate the percentage of planned progress of each activity and the percentage planned globally.

<img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/60739/content">