# Feature OP-10072 - Gantt Chart / Workpackages: Start-to-start task relation

Project: OpenProject
Status: new
URL: https://community.openproject.org/work_packages/OP-10072

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | Wish List |
| Sprint |  |
| Backlog bucket |  |
| Votes | 7 |
| List |  |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Features and Chunks

_No work packages_

## Bugs and other work packages

_No work packages_

## Technical Details

| Attribute | Value |
| --- | --- |
| Module |  |
| Feature Flag |  |
| Requires doc change | No |
| Enterprise plan |  |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups |  |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Feature Lead |  |
| Developers |  |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

**As** a _\[Project Manager\]_  
**I want to** _\[create start to start relations between tasks\]_  
**so that** _\[task have a relationship where one task cannot start until another task has begun.\]_

*   _\[Start to Start is a Logical Relationship in which a Successor Activity cannot start until a Predecessor Activity has started.\]_
*   \[**Start of a Successor Activity is Dependent on Start of the Predecessor Activity**.\]