# Bug FPCV-59 - Enabling calculated value by adding project to through custom field admin doesn't trigger calculation

Project: Feature Project - Calculated value
Status: closed
URL: https://community.openproject.org/work_packages/FPCV-59

## Open points

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Module | Administration / Custom fields |
| Target versions | 16.6.0 |
| Observed in versions |  |
| Bug found in version (deprecated) |  |
| Requires doc change | No |
| Accessibility | No |
| Pull preview |  |
| List |  |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers | Ivan Kuchin |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Planning

| Attribute | Value |
| --- | --- |
| Relevance |  |

## Costs

| Attribute | Value |
| --- | --- |
| Votes |  |
| Work |  |
| Labor costs |  |

## Description

### Steps to reproduce

1.  Create a project attribute of type calculated value with static formula or using another attribute with value for a project
    
2.  Add that project to the project attribute
    
3.  Go to the project overview page
    

### What is the buggy behaviour?

*   The for calculated value attribute is missing
    

### What is the expected behaviour?

1.  The value should have been calculated