# Bug FPCV-58 - Creating a calculated value project attribute marked required doesn't calculate values

Project: Feature Project - Calculated value
Status: closed
URL: https://community.openproject.org/work_packages/FPCV-58

## Open points

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Module | Administration / Custom fields |
| Target versions | 16.6.0 |
| Observed in versions |  |
| Bug found in version (deprecated) |  |
| Requires doc change | No |
| Accessibility | No |
| Pull preview |  |
| List |  |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers | Ivan Kuchin |
| Designer |  |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Planning

| Attribute | Value |
| --- | --- |
| Relevance |  |

## Costs

| Attribute | Value |
| --- | --- |
| Votes |  |
| Work |  |
| Labor costs |  |

## Description

### Steps to reproduce

1.  Create a project attribute of type calculated value with static formula `1 + 1` and marked **Required for all projects**
    
2.  Open overview page of any project
    

Also:

1.  Create a project attribute of type int
    
2.  Enabled the attribute for a project
    
3.  Set the value for the attribute
    
4.  Create a project attribute of type calculated value with formula using int attribute and marked **Required for all projects**
    
5.  **Open overview page of any project**
    

### What is the buggy behaviour?

*   Value for the calculated value attribute is missing
    

### What is the expected behaviour?

1.  Value for the calculated value attribute should be calculated