# Feature AGILE-303 - Work package overview on sprint report page

Project: Stream agile
Status: tested
URL: https://community.openproject.org/work_packages/AGILE-303

## Planning

| Attribute | Value |
| --- | --- |
| Date |  |
| Priority | Medium |
| Target versions | 18.0.0 |
| Sprint | Sprint 11 |
| Backlog bucket |  |
| Votes |  |
| List | Agile Reporting |
| Roadmap |  |
| Relevance |  |

## OPEN POINTS / FEEDBACK

_No work packages_

## Features and Chunks

_No work packages_

## Bugs and other work packages

| ID | Type | Subject | Status | Assignee | Target versions | Spent time | Module |
| --- | --- | --- | --- | --- | --- | --- | --- |
| AGILE-459 | Bug | Sprint report: reference dates are missing on View all link | confirmed |  | 18.0.0 |  | Modules and project features / Backlogs |
| AGILE-454 | Bug | Sprint report automatically opens when we move a wp to a sprint if sprint report was previously opened | confirmed |  | 18.0.0 |  | Modules and project features / Backlogs |

## Technical Details

| Attribute | Value |
| --- | --- |
| Module | Modules and project features / Backlogs |
| Feature Flag |  |
| Requires doc change | Yes |
| Enterprise plan | Community (COM) |

## Details

| Attribute | Value |
| --- | --- |
| Pull preview |  |
| Mockups | https://www.figma.com/design/owpxg3fdqZONIGL6SBSG8M/Agile--Sprint-reports?node-id=1-73994&t=vj4zYlvGRDOURFuL-1 |
| Accessibility | No |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable |  |
| Product manager |  |
| Developers | Tobias Dillmann |
| Designer | Julia Racsko |
| Ordered by |  |
| Signed off by |  |
| Interest by |  |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| PD (min) |  |
| PD (max) |  |
| Work |  |
| Labor costs |  |

## Description

Follows <mention class="mention" data-id="AGILE-296" data-type="work_package" data-text="###AGILE-296">###AGILE-296</mention>

**As** an agile user  
**I want to** have an overview over the work packages that are part of the sprint  
**so that** I can quickly take in the key figures

**Acceptance criteria**

  - The sprint report page has a widget showing figures about the work packages of the sprint

  - The widget is titled "Work packages within the sprint"
    
      - If possible, the number of work packages currently associated to the sprint are displayed as a pill after the title

  - The widget has a progress bar depicting the number of total work packages, the number of finished work packages and the percentage that results in.
    
      - The widget deliberately does not span the whole width on wide screens. The exact width will need to be identified during implementation.

  - The widgets shows an additional row of information blocks below the progress bar:
    
      - Each block has a heading, a number representing the total number of work packages and a number representing the sum of story points for those work packages.
        
          - Next to each heading is a "View all" link points to a baseline table view: the reference date (see the blocks) is the sprint start or finish date.
        
          - When baseline is not active on the instance, this link is not shown
    
      - The information blocks for work packages are:
        
          - "Initially planned" - those are the work packages assigned to the sprint on sprint start. The sprint start is the sprint start date.
            
              - Reference date: sprint start or current date (the earlier of the two)
        
          - "Scope change" - the total of work packages added or removed from the sprint.
            
              - Both added and removed should be tallied separately. This is also true for the story points.
            
              - Reference date: Interval between sprint start and the sprint finish date (or the current date if that is earlier).
        
          - "Completed" - those are work packages considered finished
            
              - Reference date: sprint finish or current date (the earlier of the two)
            
              - The number representing the total number of work packages is green.
        
          - "Unfinished"- those are work packages not considered finished.
            
              - Reference date: sprint finish or current date (the earlier of the two)
            
              - The number representing the total number of work packages is grey.
    
      - The information blocks are displayed in a single line (4x1) if space permits. If there is less width, that changes to a 2x2 layout and eventually to a 1x4 layout.
        
          - The exact breakpoints will need to be identified during implementation

  - A blankslate is displayed covering the whole widget if the sprint's start/finish dates are not set.

Notes:

  - "Finished" always refers to the work packages that have a status considered closed in the project (backlogs settings)

  - Some layout decisions will need to be taken during implementation. Contact <mention class="mention" data-id="100056" data-type="user" data-text="@Julia Racsko">@Julia Racsko</mention> for confirmation.

  - While the sprint start and finish dates are dates (whithout time zones) the current user's local time for start or end of the day of that date is used.

  - If possible, the actual sprint start and completion times should be used as defined in <mention class="mention" data-id="78631" data-type="work_package" data-text="###AGILE-399" data-display-id="AGILE-399">\#\#\#AGILE-399</mention>

**Technical notes**

<br>

**Permissions and visibility considerations**

  - Users having the "view sprints" permission can see the sprint goal widget

**Translation considerations**

  - 
    <br>

**Out of scope**

  - Configuring the widget

  - Displaying a different unit than story points (this will change with <mention class="mention" data-id="74098" data-type="work_package" data-text="###AGILE-198" data-display-id="AGILE-198">\#\#\#AGILE-198</mention>