# Epic AGILE-10 - Burndown chart

Project: Stream agile
Status: in development
URL: https://community.openproject.org/work_packages/AGILE-10

## Detailed specification

### Motivation and background information

### Acceptance criteria

*   Chart functionality that works on journal entries
    
*   Show diagram
    
    *   x-axis: time
        
        *   indicate non-working days with a gray background
            
    *   y-axis: the amount of work left to complete, measured in either story points, days or number of issues
        
    *   The red line: shows the work that was planned for the sprint. It can increase through the sprint to show scope changes. It should decrease through the sprint duration, which would indicate that the work was delivered.
        
    *   The gray line: shows an approximation of how your team should be progressing throughout the sprint.
        
*   Widget
    
    *   Overview
        
    *   Dashboard
        
    *   Sprint reports view
        
*   Add filter/configuration options to burndown chart widget (similar to work package graph)
    
    *   Define if you would like to use days, number of issues or story points on y-axis
        
*   Filter for:
    
    *   Version
        
    *   Sprint
        
    *   Project phase

### Out of scope

| Attribute | Value |
| --- | --- |
| Mockups | https://www.figma.com/design/kjzHe0qOLme1LXCjLoTBFV/Overview-and-Dashboard?node-id=1946-5672&t=LFnyM5QOWMNC5Otu-1 |

## Planning

| Attribute | Value |
| --- | --- |
| Roadmap | 2026 Q4 |
| Date |  |
| Votes | 1 |
| List | RM Jira exit, RM Agile, Agile Reporting |
| Target versions | 18.0.0 |
| Sprint |  |
| Backlog bucket |  |
| Relevance | Important — Required Short-Term |

## Subitems

_No work packages_

## Bugs and other work packages

_No work packages_

## Details

| Attribute | Value |
| --- | --- |
| Module |  |
| Enterprise plan | Community (COM) |
| Labels |  |

## People

| Attribute | Value |
| --- | --- |
| Assignee |  |
| Accountable | Rosanna Sibora |
| Product manager | Rosanna Sibora |
| Designer | Julia Racsko |
| Developers | OP Dev Polaris Team |
| Requested by |  |
| Interest by | Lababa (37618), Tiziano (37949), Black (37919), Joules (39703), Home (224196000003952096) |

## Estimates and progress

| Attribute | Value |
| --- | --- |
| Work | 30d 0h |

## Description

**As** a project manager  
**I want to** have a burndown chart as a widget on the project overview and in the sprint report  
**so that** I can quickly see the status of the work packages contained in my project.

<br>